What Is a BOQ? Bill of Quantities Explained
A bill of quantities (BOQ) is an itemised list of every material, quantity of work and labour item on a construction project, each with a description, a unit of measurement, a quantity and a rate. Add up the line items and you get the tender price. It is the document contractors price against, clients compare bids with, and quantity surveyors use to value work as a job progresses. A BOQ is not a guess and not a shopping list. It is a measured, priced schedule — and on any job bigger than a single room, it is what keeps the budget honest. A standard BOQ has four parts: preliminaries (site setup, scaffolding, insurance, supervision), measured work (excavation, concrete, masonry, carpentry, finishes, plumbing and electrical), provisional sums (allowances for work that can't be measured yet), and dayworks (labour, plant and materials charged by the hour or day).
💡 At a Glance
A bill of quantities is the measured, priced schedule of all work on a project — every item described, measured in the right unit, and priced — so every bidder prices the same job.
ƒx Key Formula
Line total = quantity × rate; slab volume (cu yd) = L × W × (T ÷ 12) ÷ 27; bags = cu ft ÷ 0.60 per 80 lb bag
Step-by-Step Takeoff
-
1
Take off the quantities. Measure every item from the drawings — lengths, areas, volumes, counts. This is the takeoff, and it is where most BOQ errors are born. Use the Takeoff tool to keep the measurements in one place.
-
2
Describe each item properly. "Concrete, M20 grade, 150 mm thick, in slab" — not "concrete". The description is the specification. A line that says only "concrete" with no thickness, mix or location is useless — two bidders will price two different jobs.
-
3
Pick the right unit. Concrete in cubic yards or cubic metres, formwork in square feet, rebar in kilograms or pounds, doors in numbers. Wrong unit, wrong price.
-
4
Apply rates. Multiply quantity × rate for each line. Rates come from your own cost records or supplier quotes — never from memory.
-
5
Add waste and check. Add a waste allowance per material (typically 5–10%), then read the whole BOQ once looking for missing items: excavation without disposal, walls without plaster, roofs without flashing.
-
6
Worked example: a 10 × 10 ft patio slab, 4 inches thick, on a 4-inch gravel base. Excavate topsoil and level 100 sq ft; compacted gravel base 1.23 cu yd; concrete 1.23 cu yd (10 × 10 ft × 4 in = 33.3 cu ft ÷ 27); 59 eighty-pound bags with 5% waste (33.3 ÷ 0.60 = 56 bags); formwork 40 lin ft; curing 7 days. Check the same numbers in the Concrete Calculator.
-
7
Know the three documents: the takeoff is the measured quantities with no prices, first; the estimate is quantities plus approximate rates for budgeting, before tender; the BOQ is quantities plus firm descriptions plus tender rates — the pricing document. The takeoff feeds the estimate, and the estimate hardens into the BOQ.
⚠️ Common Mistakes
-
1
Vague descriptions. "Brickwork" with no brick type, bond or mortar mix invites three different prices for one line.
-
2
Missing waste. Ordering exact quantities means a short delivery mid-pour. Add 5–10% per material.
-
3
Forgetting preliminaries. Scaffolding, site cabins and supervision are real costs — if they aren't in the BOQ, they come out of profit.
-
4
No provisional sums. Undecided items (fixtures, specialist work) need an allowance line, or the first change order becomes a dispute.
-
5
Mixing units. Square feet for one wall and square metres for the next guarantees an arithmetic error somewhere.
Guide FAQ
What does BOQ stand for?
Bill of Quantities — the priced, itemised schedule of all work on a construction project.
Who prepares a BOQ?
Usually a quantity surveyor, working from the architect's or engineer's drawings. On small jobs the contractor or builder prepares it.
Is a BOQ the same as an estimate?
No. An estimate is an approximate budget. A BOQ is a measured, priced tender document — every quantity is taken off the drawings and every line is priced.
What is a provisional sum in a BOQ?
An allowance for work that can't be fully measured or specified yet, priced later when the details are known.
Do small residential jobs need a BOQ?
For a single room, a detailed estimate is usually enough. For a full house, extension or any job with multiple trades, a BOQ pays for itself in fewer disputes.
Related Guides
How Many Bags of Concrete for a 10×10 Slab?
Bag count, cubic yards, and cost for the classic 10x10 patio slab at 4 inches thick. Includes ready-mix breakpoint and curing plan.
How Much Gravel for a Driveway?
Cubic yards, tons, delivery cost, and base depth for a 20x40 ft driveway at 4 inches deep.
How Much Rebar for a Slab Grid?
Bar counts, lap splices, chairs, ties, and weight for a 20x20 ft slab grid at 18 in o.c.