How Much Backfill for a 20×10 ft Trench?

A 20×10 ft trench 4 ft deep is 800 cubic feet of bank soil — 29.6 cubic yards before anything else happens. Then two things grow the order: 10% over-excavation for workspace, and 15% compaction, because backfill shrinks as it is compacted. The order lands at 38.3 cubic yards, about 50 tons of native soil, and 4 truck trips at 10 yards a load. This guide works the exact calculator math and shows how material choice moves the number.

💡 At a Glance

A 20×10×4 ft trench is 29.6 cu yd bank — order 38.3 cu yd with 10% over-excavation and 15% compaction, about 50 tons and 4 truck trips.

ƒx Key Formula

Bank yd = L × W × D ÷ 27; order = bank × 1.10 ÷ (1 − compaction); trips = ceil(order ÷ truck capacity); weight = order × density ÷ 2000

Step-by-Step Takeoff

  1. 1

    Measure the trench: 20 ft long, 10 ft wide, 4 ft deep — the calculator defaults.

  2. 2

    Bank volume = 20 × 10 × 4 = 800 cu ft ÷ 27 = 29.63 cu yd. Bank yards are soil in the ground, before digging.

  3. 3

    Add over-excavation for workspace: 29.63 × 1.10 = 32.59 cu yd.

  4. 4

    Add compaction: the order = 32.59 ÷ (1 − 0.15) = 38.34 cu yd. You order more than the hole because compaction shrinks the fill.

  5. 5

    Compacted volume in place = 32.59 × (1 − 0.10 shrink) = 29.33 cu yd — the fill settles back near bank volume once compacted.

  6. 6

    Weight = 38.34 cu yd × 2,600 lb per cu yd ÷ 2,000 = 49.8 tons of native soil.

  7. 7

    Trucks = 38.34 ÷ 10 cu yd per truck = 4 trips (rounded up). Compare materials in the Backfill Calculator — gravel shrinks only 6%, sand 8%, clay swells 28% and needs the biggest order.

🧮 Backfill · Open calculator
Backfill · More guides →

⚠️ Common Mistakes

  • 1

    Ordering bank volume without compaction — the order runs about 30% short once the fill is compacted.

  • 2

    Ignoring swell on clay — 28% swell is the highest of the four materials and blows up the truck count.

  • 3

    Booking trucks by bank yards — trucks haul the loose order volume (38.3 yd here), not the 29.6 bank yards.

Guide FAQ

Why order 38 yards for a 30-yard hole?

Compaction and over-excavation: 29.6 bank yards become 32.6 with workspace, then 38.3 once compaction is added.

What is the difference between swell and shrink?

Swell is loose soil taking more space after digging (native 20%); shrink is the settling when it is compacted (native 10%). The calculator applies both.

How many truck trips for 38 yards?

Four trips at 10 cubic yards per truck — the calculator rounds up, so a half-load still costs a trip.

Which backfill material compacts best?

Gravel, at 6% shrink versus 10% for native soil and 15% for clay. Clay also swells the most at 28%.

What is over-excavation?

Digging about 10% beyond the foundation line for working room — the calculator adds it to the volume before compaction.