🏗️ Worked Example
⏱ 1 min read

什么是 BOQ?工程量清单(Bill of Quantities)详解

工程量清单(BOQ)是建筑项目中每种材料、工程量和人工项目的逐项清单,每项都包含说明、计量单位、数量和单价。把所有清单项加起来就是投标价。它是承包商据以报价、客户据以比较投标、工料测量师(quantity surveyor)据以按工程进度计价的文件。BOQ 不是猜测,也不是购物清单。它是一份经过计量和计价的清单——在任何大于单个房间的工程中,正是它让预算保持真实。一份标准 BOQ 由四部分组成:preliminaries(现场布置、脚手架、保险、监理)、measured work(土方、混凝土、砌体、木工、装修、给排水和电气)、provisional sums(尚无法计量的工程的预留款),以及 dayworks(按小时或按天计费的人工、机械和材料)。

💡 At a Glance

A bill of quantities is the measured, priced schedule of all work on a project — every item described, measured in the right unit, and priced — so every bidder prices the same job.

ƒx Key Formula

Line total = quantity × rate; slab volume (cu yd) = L × W × (T ÷ 12) ÷ 27; bags = cu ft ÷ 0.60 per 80 lb bag

Step-by-Step Takeoff

  1. 1

    算出工程量(takeoff)。根据图纸测量每一项——长度、面积、体积、数量。这就是 takeoff,也是大多数 BOQ 错误的来源。使用 Takeoff tool 把所有测量数据集中在一处。

  2. 2

    正确描述每一项。"Concrete, M20 grade, 150 mm thick, in slab"——而不是"concrete"。说明就是规范。只写"concrete"、没有厚度、配比或位置的清单行毫无用处——两个投标人会报出两个不同工程的价格。

  3. 3

    选择正确的单位。Concrete in cubic yards or cubic metres,模板 in square feet,钢筋 in kilograms or pounds,门按 numbers 计。单位错了,价格就错了。

  4. 4

    套用单价。每行用 quantity × rate 相乘。单价来自你自己的成本记录或供应商报价——绝不要凭记忆。

  5. 5

    加上损耗并检查。每种材料加上损耗 allowance(通常为 5–10%),然后通读整份 BOQ,查找遗漏项:没有弃土的开挖、没有抹灰的墙、没有泛水的屋顶。

  6. 6

    实例:一块 10 × 10 ft 的 patio slab,厚 4 inches,铺在 4-inch gravel base 上。开挖表土并平整 100 sq ft;压实碎石基层 1.23 cu yd;混凝土 1.23 cu yd(10 × 10 ft × 4 in = 33.3 cu ft ÷ 27);含 5% 损耗共 59 袋 80 lb 水泥袋(33.3 ÷ 0.60 = 56 bags);模板 40 lin ft;养护 7 days。在 Concrete Calculator 中核对相同的数字。

  7. 7

    了解三份文件:takeoff 是先算出的计量数量,不含价格;estimate 是数量加概算单价,用于投标前编制预算;BOQ 是数量加明确说明加投标单价——即计价文件。Takeoff 生成 estimate,estimate 再落实为 BOQ。

🧮 Concrete · Open calculator
Concrete · More guides →

⚠️ Common Mistakes

  • 1

    Vague descriptions. "Brickwork" with no brick type, bond or mortar mix invites three different prices for one line.

  • 2

    Missing waste. Ordering exact quantities means a short delivery mid-pour. Add 5–10% per material.

  • 3

    Forgetting preliminaries. Scaffolding, site cabins and supervision are real costs — if they aren't in the BOQ, they come out of profit.

  • 4

    No provisional sums. Undecided items (fixtures, specialist work) need an allowance line, or the first change order becomes a dispute.

  • 5

    Mixing units. Square feet for one wall and square metres for the next guarantees an arithmetic error somewhere.

Guide FAQ

BOQ 是什么意思?

Bill of Quantities——建筑项目全部工程的计价逐项清单。

谁编制 BOQ?

通常由工料测量师(quantity surveyor)根据建筑师或工程师的图纸编制。小工程由承包商或施工方编制。

BOQ 和 estimate 是一回事吗?

不是。Estimate 是概算预算。BOQ 是经过计量和计价的投标文件——每个数量都从图纸上算出,每行都计价。

BOQ 中的 provisional sum 是什么?

为尚无法完全计量或明确的工程预留的款项,待细节确定后再计价。

小型住宅工程需要 BOQ 吗?

单个房间的话,一份详细的 estimate 通常就够了。对于整栋房屋、扩建或涉及多个工种的工程,BOQ 能减少争议,物有所值。