How Much Plywood for Shuttering a 20×10 Slab?
Shuttering is ordered by contact area — the surface of concrete that touches formwork. A 20×10 ft slab touches formwork on its bottom only: 200 sq ft. At 4×8 sheets (32 sq ft each) with the calculator default 10% waste, that is 7 sheets, plus 4 litres of shuttering oil at 50 sq ft per litre. Beams, columns, and staircases count differently — bottom plus sides — so this guide works the slab example and the three other member formulas.
💡 At a Glance
A 20×10 ft slab needs 200 sq ft of formwork — 7 sheets of 4×8 plywood with 10% waste and 4 litres of shuttering oil.
ƒx Key Formula
Slab area = L × W; beam = (W + 2D) × L; column = 2 × (W + D) × H; sheets = ceil(area ÷ sheet area × 1.10); oil (L) = area ÷ 50
Step-by-Step Takeoff
-
1
Pick the member type: slab here. The calculator defaults to a 20×10 ft slab, 8 in deep, one member.
-
2
Slab contact area = length × width = 20 × 10 = 200 sq ft (bottom surface only).
-
3
Sheet area = 4 × 8 ft = 32 sq ft (a 4×10 sheet is 40 sq ft).
-
4
Sheets = 200 ÷ 32 × 1.10 waste = 6.88, rounded up to 7 sheets. With 4×10 sheets it is 6.
-
5
Shuttering oil = 200 ÷ 50 sq ft per litre = 4 litres (about 1.06 gallons) — the release agent that lets plywood strip cleanly.
-
6
Beam area = (width + 2 × depth) × length: bottom plus two sides. Column area = 2 × (width + depth) × height: all four faces. Staircase adds the waist and sides to the slab area.
-
7
Enter your member type, dimensions, and waste percentage in the Shuttering Calculator for the exact sheet, oil, and cost totals.
⚠️ Common Mistakes
-
1
Counting only the slab bottom for beams — a beam adds both sides, so the area is several times the bottom alone on deep members.
-
2
Ordering the exact sheet count without waste — one bad cut and you are short a matching sheet.
-
3
Skipping shuttering oil — plywood bonds to concrete and tears on stripping without it.
Guide FAQ
How many plywood sheets for a 20×10 slab?
7 sheets of 4×8 with 10% waste — 6 sheets if you use 4×10 stock.
What is shuttering oil for?
A release agent brushed on plywood so it strips off cured concrete cleanly — the calculator allows 50 sq ft per litre.
Why do beams need more formwork than slabs?
A slab counts the bottom only; a beam counts bottom plus two sides, and a column counts all four faces.
4×8 or 4×10 sheets?
4×10 covers 40 sq ft per sheet — fewer sheets and fewer joints on long runs; the calculator prices both.
How much waste should I allow?
10% is the calculator default — raise it for cut-up layouts with many short pieces.
Related Guides
How Many Bags of Concrete for a 10×10 Slab?
Bag count, cubic yards, and cost for the classic 10x10 patio slab at 4 inches thick. Includes ready-mix breakpoint and curing plan.
How Much Rebar for a Slab Grid?
Bar counts, lap splices, chairs, ties, and weight for a 20x20 ft slab grid at 18 in o.c.
How Much Lumber for a 16×20 Deck Frame?
Joists, beams, posts, decking board feet, and hardware for a 16x20 deck frame.