👷️ Worked Example
⏱ 2 min read

How Much Does a 4-Worker Crew Cost for 5 Days?

Four workers at 8 hours a day for 5 days is 160 person-hours. At $35 an hour the base wages are $5,600; a 30% burden adds $1,680, and a 3% contingency adds $218.40 — so the week costs $7,498.40, or $374.92 per worker-day. Per diem and tools are $0 in the defaults, so add them when the crew travels or rents equipment; the worked example below uses the defaults only. This guide works the crew example from the Crew Labor Calculator, including the overtime comparison.

💡 At a Glance

A 4-worker crew for 5 days costs $7,498.40 — 160 person-hours at $35, plus 30% burden and 3% contingency; $374.92 per worker-day.

ƒx Key Formula

Person-hours = workers × hours/day × days; wages = hours × rate; burden = wages × burden%; total = wages + burden + per diem + tools + 3% contingency

Step-by-Step Takeoff

  1. 1

    Person-hours = 4 workers × 8 hours × 5 days = 160 regular hours. Overtime is 0 in the defaults.

  2. 2

    Base wages = 160 × $35 = $5,600.00.

  3. 3

    Burden = 30% × $5,600 = $1,680.00 — the payroll overhead on top of the hourly rate; set it to your local practice.

  4. 4

    Per diem and tools are $0 in the defaults — add them if the crew travels or rents equipment. A $25 per diem would add 4 × 5 × $25 = $500 before contingency.

  5. 5

    Contingency = 3% × ($5,600 + $1,680) = $218.40. It applies to wages plus burden plus per diem plus tools.

  6. 6

    Grand total = $5,600.00 + $1,680.00 + $218.40 = $7,498.40.

  7. 7

    Unit costs: $7,498.40 ÷ 20 worker-days = $374.92 per worker-day; ÷ 160 hours = $46.86 per person-hour. With 2 overtime hours a day at 1.5×, the week becomes $10,310.30. Enter your crew in the Crew Labor Calculator.

🧮 Crew Labor · Open calculator
Crew Labor · More guides →

⚠️ Common Mistakes

  • 1

    Budgeting wages only — burden adds 30% and contingency 3% here; the wage number is barely three-quarters of the real cost.

  • 2

    Forgetting that overtime multiplies the rate — 2 hours a day at 1.5× adds $2,100 to this week, not $1,400 at straight time.

  • 3

    Applying contingency to wages alone — the calculator applies it to wages plus burden plus per diem plus tools; on this crew that is $218.40, not $168.00.

Guide FAQ

How much does a 4-worker crew cost for a week?

$7,498.40 — $5,600 wages, $1,680 burden, and $218.40 contingency.

What is the cost per worker-day?

$374.92 — the $7,498.40 total divided by 20 worker-days.

What does burden add?

30% on wages — $1,680 here. It is the payroll overhead on top of the hourly rate, and the calculator leaves the percentage to your local practice — it is not a payroll tax calculation.

What does 2 hours of overtime a day cost?

40 overtime hours at $52.50 an hour is $2,100, taking the week to $10,310.30.

Is contingency on wages only?

No — 3% on wages plus burden plus per diem plus tools; on this crew that is $218.40, not $168.00.