A 1000 sq ft roof slab at 5 inches thick in M20 grade (1:1.5:3) needs about 95 fifty-kg cement bags, 175 CFT sand and 350 CFT aggregate. Select M20 in the Concrete Calculator grade dropdown and it computes all three instantly — this guide shows the hand math so you can check any estimate.

💡 At a Glance

A 1000 sq ft M20 slab at 5 in needs about 95 bags of 50 kg cement, 175 CFT sand, and 350 CFT aggregate.

ƒx Key Formula

Dry volume = wet × 1.54; cement bags = dry cement CFT × 1440 kg/m³ ÷ 50 kg

Step-by-Step Takeoff

  1. 1

    Volume: 1000 sq ft x 0.416 ft = 416 CFT wet volume.

  2. 2

    Dry volume: 416 x 1.54 = 641 CFT of dry material.

  3. 3

    M20 split 1:1.5:3 over 5.5 parts: cement 117 CFT, sand 175 CFT, aggregate 350 CFT.

  4. 4

    Cement: 117 CFT ≈ 3.31 m³ × 1440 kg/m³ ÷ 50 kg ≈ 95 bags; sand 175 CFT; aggregate 350 CFT.

  5. 5

    Add 5% wastage on cement, 7% on sand and aggregate for handling losses.

  6. 6

    Order water for curing too: ponding a 1000 sq ft slab needs roughly 2000 litres over 7 days.

  7. 7

    Price it with your local 50 kg bag rate in the calculator and export the quote.

🧮 Concrete · Open calculator
Concrete · More guides →

⚠️ Common Mistakes

  • 1

    Ordering wet volume directly — the 1.54 dry-volume factor is what the supplier orders against.

  • 2

    Ignoring wastage — add 5% on cement and 7% on sand and aggregate for handling losses.

  • 3

    Stopping curing at 7 days on a roof slab — keep it wet 14 days minimum and props in 14–21 days.

Guide FAQ

M20 or M25 for a roof slab?

M20 is standard for residential roof slabs; use M25 for heavy loads or commercial spans.

Why 50 kg bags?

Indian cement sells in 50 kg bags; one bag is about 1.24 CFT.

How much sand for 1000 sq ft slab?

About 175 CFT (roughly 6 brass) for M20 at 5 inches.

What is one brass in CFT?

100 CFT — sand and aggregate are commonly quoted per brass.

How many days to cure a roof slab?

Keep it wet 14 days minimum for roof slabs; props stay 14–21 days.