⛏️ Excavation Calculator PRO

Volume, compaction, equipment, hauling, backfill, benching & cost — all in one.

Advertisement
Ad space — activates after AdSense approval

Pit Cross-Section — updates as you type

Dig profile with sloped sides. Bank volume converts to loose yards for hauling.

V = L x W x D / 27 = cu yd

1 Excavation Type

2 Dimensions

3 Soil Type

Density—
Swell Factor—
Shrinkage—
Bench Angle—

4 Compaction

Calculate Compaction (Loose vs Compacted)
Bank Volume—
Loose Volume (after swell)—
Compacted Volume—
Cut vs Fill Difference—

5 Equipment

Bucket Size—
Cycle Rate—
Production—

6 Hauling

Material to Haul (loose)—
Total Trips—
Haul Duration—
Trucks Needed—

7 Backfill

Calculate Backfill & Compaction Layers
Backfill Volume—
Compacted Layers—
Fill Material Needed—

8 Benching / Sloping

Calculate Benching/Sloping (OSHA)
Required Slope (H:V)—
Excavation Width at Top—
Additional Excavation—
Max Depth (no benching)—

OSHA Table D-1 (Sloping/Benching):

  • Stable rock: Vertical (90°)
  • Type A (clay): ¾:1 (53°)
  • Type B (sand/gravel): 1:1 (45°)
  • Type C (loose): 1½:1 (34°)

9 Labour & Cost

Results

Volume

Cubic Feet—
Cubic Yards (Bank)—
Cubic Meters—
Tons—

Compaction

Loose Volume—
Compacted Volume—
Shrinkage—

Equipment

Machine—
Production Rate—
Operating Hours—
Fuel Cost—

Hauling

Trips Required—
Haul Duration—
Haul Cost—
Disposal Cost—

Backfill

Backfill Volume—
Compacted Layers—
Fill Material Cost—

Cost Breakdown

Equipment Cost—
Fuel Cost—
Operator Cost—
Haul Cost—
Disposal Fee—
Backfill Material—
Permit—
Labour—

Subtotal—
Contingency (%)—
Safety Factor (%)—

Grand Total—
Cost per Cu Yd—

⚠️ Pre-Export Checklist

  • Dimensions verified on-site
  • Soil composition tested (geotechnical report)
  • Underground utilities located (Call 811)
  • Access road for trucks confirmed
  • Disposal site identified and permitted
  • OSHA excavation permit obtained (depth >5 ft)
  • Sloping/benching plan reviewed
  • Dewatering plan (if water table nearby)
  • Environmental permits obtained
  • Safety barriers and signage arranged

Professional Excavation Estimation Guide

Show formulas, worked examples & pro tips ▼

Formulas

Bank Volume= Length × Width × Depth (cubic feet ÷ 27 = cubic yards)

Loose Volume= Bank Volume × (1 + Swell Factor / 100)

Compacted Volume= Bank Volume × (1 − Shrinkage Factor / 100)

Equipment Hours= Volume ÷ Production Rate (cu yd/hr)

Truck Trips = Loose Volume ÷ Truck Capacity

Haul Duration= Trips × Round-Trip Time ÷ (60 × Number of Trucks)

Trench (trapezoidal)= ((Bottom Width + Top Width) ÷ 2) × Depth × Length

Top Width= Bottom Width + 2 × (Depth × Slope Ratio)

Soil Types & Factors

SoilDensity (lb/cu yd)Swell %Shrinkage %OSHA Type
Clay2,70025-40%10-15%Type A (53°)
Sand2,40010-15%5-10%Type B (45°)
Gravel2,50012-20%5-8%Type B (45°)
Rock2,80030-50%2-5%Vertical
Mixed2,60020-30%8-12%Type B (45°)

Worked Example — Foundation Excavation

30 ft × 20 ft × 4 ft deep, Clay soil, Standard excavator, 10 cu yd trucks:

  • Bank Volume: 30 × 20 × 4 = 2,400 cu ft = 88.9 cu yd
  • Loose Volume (clay 30% swell): 88.9 × 1.30 = 115.6 cu yd
  • Weight: 88.9 × 2,700 lb = 240,030 lbs = 120 tons
  • Equipment (std excavator ~80 cu yd/hr): 88.9 ÷ 80 = 1.1 hours
  • Truck trips: 115.6 ÷ 10 = 12 trips
  • Haul (45 min round trip, 2 trucks): 12 × 45 ÷ (60 × 2) = 4.5 hours
  • Backfill: 88.9 − 12 (structure) = 76.9 cu yd needed
  • Layers (12" each, 4 ft depth): 4 layers of 12" lifts

Equipment Selection Guide

  • Mini Excavator (1-3 cu yd/hr): Trenches, tight access, light grading
  • Standard Excavator (50-120 cu yd/hr): Foundations, basements, pools
  • Backhoe (30-80 cu yd/hr): Utility trenches, small foundations
  • Dozer (100-300 cu yd/hr): Large grading, bulk earthmoving
  • Skid Steer (10-30 cu yd/hr): Backfill, compaction, tight areas

Common Mistakes to Avoid

  • Not accounting for swell — loose clay takes 30-40% more truck space
  • Ignoring OSHA sloping — depths over 5 ft require sloping or shoring
  • Not testing soil composition — wrong assumptions lead to wrong costs
  • Forgetting compaction shrinkage — backfill needs 10-15% more material
  • Underestimating hauling — round-trip time is often 30-60 minutes
  • Not calling 811 (Call Before You Dig) — underground utilities are common
  • Skiping dewatering planning — water table issues can double costs

Pro Tips

  • Keep topsoil separate — it is valuable for landscaping restoration
  • Stockpile excavated material on-site if space allows for backfill savings
  • Use geotextile fabric between backfill layers to prevent soil migration
  • Compact in 8-12 inch lifts — thicker lifts won't achieve required density
  • Wet soil during compaction for optimal density (but not over-saturated)
  • Always have a spotter when working near utilities or structures
  • Check weather — rain can flood open excavations and destabilize walls
  • Document everything — photos of conditions protect against disputes
⛏️

Drag to rotate — Scroll to zoom

L: ft × W:ft × D: ft
Volume:cu yd
Legend
Soil
Excavation (cut)
Equipment
Grass / Surface
Dimensions
Soil:—

Client & Quote (prints on PDF & Excel)

Adjustments (applies to exports)

Contingency is added as a separate line on the exported cost summary. Waste % is printed as an advisory reminder.

Project notes (prints on PDF & Excel)

Result compare (A/B)

Item Pinned Current Change

Saved rates auto-apply from your Price Library. Advanced details stay in your browser — nothing is uploaded except inside your own PDF/Excel exports.

Advertisement
Ad space — activates after AdSense approval

يمكنك استخدام حاسب حفر المجاني برضنا لتقدير كميات المواد المطلوبة لمشروعك البناء الخاص بك. يدعمك الحاسب تقديرات فورية مدونة.

📖 كيف تستخدم هذا الحاسب

1

كيف تستخدم هذا الحاسب

📐 افهم حساب حفر

الصيغة الأساسية هي: الحجم = الطول × العرض × العمق. تحول الحجم إلى الوحدة المطلوبة.

⚠️ أخطأ شائعة للتجنب

✕

استخدام وحدود خاطئة

✓ تأكد استخدام وحدود متساوية في الحساب.

✕

نسيان الهضر

✓ أضف دائماً معدوداً.

💡 نصائح مهنا

✓

الطلب دائماً مزيدًا.

✓

تحقق من كود البناء المحلي.

✓

اطلب المواد مسبقًا.

❓ أشفاع مشهورة

أدخل أبعاد مشروعك والتقديرات الفورية ضرورياً.

🏗️ تطبيقات في الحيات الواقعة

يعمل حاسب حفر المجاني على مشروعات مختلفة.

الحاسب المجاني المجاني لتقدير earth volume and trucks.

✅Method, Sources & Review

Maintained by theBuildingCalc methods desk· Last reviewedSeptember 23, 2026. This calculator implements the standards and references below; every figure can be rechecked against the formulas and worked example on this page.

OSHA 29 CFR 1926 Subpart P USCS soil classes

Results are estimates, not engineering advice. Verify against local codes and licensed professionals for structural, electrical, and gas work. See ourTerms. Spotted an error? Report it— corrections ship with the next review.