M20 Concrete for a 1000 sq ft Slab in India

A 1000 sq ft roof slab at 5 inches thick in M20 grade (1:1.5:3) needs about 90 fifty-kg cement bags, 170 CFT sand and 340 CFT aggregate. Select M20 in the Concrete Calculator grade dropdown and it computes all three instantly โ€” this guide shows the hand math so you can check any estimate.

Step-by-Step Takeoff

  1. 1

    Volume: 1000 sq ft x 0.416 ft = 416 CFT wet volume.

  2. 2

    Dry volume: 416 x 1.54 = 641 CFT of dry material.

  3. 3

    M20 split 1:1.5:3 over 5.5 parts: cement 117 CFT, sand 175 CFT, aggregate 350 CFT.

  4. 4

    Cement: 117 CFT x 1440 kg/m3 / 50 kg = about 90 bags; sand 175 CFT; aggregate 350 CFT.

  5. 5

    Add 5% wastage on cement, 7% on sand and aggregate for handling losses.

  6. 6

    Order water for curing too: ponding a 1000 sq ft slab needs roughly 2000 litres over 7 days.

  7. 7

    Price it with your local 50 kg bag rate in the calculator and export the quote.

๐Ÿงฎ Concrete ยท Open calculator
Concrete ยท More guides โ†’

Guide FAQ

M20 or M25 for a roof slab?

M20 is standard for residential roof slabs; use M25 for heavy loads or commercial spans.

Why 50 kg bags?

Indian cement sells in 50 kg bags; one bag is about 1.24 CFT.

How much sand for 1000 sq ft slab?

About 175 CFT (roughly 6 brass) for M20 at 5 inches.

What is one brass in CFT?

100 CFT โ€” sand and aggregate are commonly quoted per brass.

How many days to cure a roof slab?

Keep it wet 14 days minimum for roof slabs; props stay 14โ€“21 days.