🏗️ Concrete Calculator

Volume, rebar, formwork, material breakdown & cost — all in one.

Dimension Diagram — updates as you type

Slab plan view. Length × width gives the area; thickness gives the depth of the pour.

Ring plan view. The strip runs around the perimeter; corners are counted once, not twice.

V = L × W × T  →  ÷ 27 = cu ydV = (Lout + internal) × width × depth  →  ÷ 27 = cu yd

1 Project Type

2 Shape

3 Dimensions

Measure internal walls wall-to-wall (clear lengths). Corners are counted once; internal walls are added separately.

4 Rebar (Optional)

Include Rebar Calculation

5 Options

—

Designed Mix — by Strength Class

A designed mix for a target strength, not a fixed ratio. Pick the class and the calculator works out water, cement, sand and coarse aggregate by the absolute-volume method.

Designed mix is per cubic metre. Job totals below use your volume above, with the same waste %.

Labour Cost

Results

Volume

Cubic Feet—
Cubic Yards—
Cubic Meters—
Liters—

Strip Footing Ring

Centreline Length (Lout)—
Ring Area—
Outer Ring Volume—
Internal Walls Volume—

Strip Footing — Formwork & Rebar Detail

Board rows—
Total board length—
Board area—
Board volume—
Boards needed (16 ft)—
Lap length—
Stock bars per line—
Longitudinal stock bars—
Stirrup size—
Stirrup length—
Stirrups — main strip—
Stirrups — internal walls—
Stirrups total—
Total stirrup length—
Stirrup bars needed (20 ft)—
Stirrup weight—

Bags Needed

—

Material Breakdown (approximate)

Cement—
Sand—
Gravel—
Water—
Mix Ratio—
Cement (50 kg)—
Sand—
Aggregate—

Designed Mix — per m³

Water / cement ratio—
Water—
Cement—
50-kg bags per m³—
Sand—
Coarse aggregate—
Proportions by mass (cement : sand : coarse)—
Proportions by volume (cement : sand : coarse)—
Absolute volumes sum—
Per cubic yard—
Designed mix — this job (incl. waste)
Cement—
Sand—
Coarse aggregate—
Water—

Rebar

Bars Needed—
Total Length—
Total Weight—
Cost—

Formwork

Form Area—
Form Perimeter—

Cure Time

Walk on—
Full Cure—
Concrete Cost—
Rebar Cost—
Material Cost—
Labour Cost—

Grand Total—
🧩Embed

⚠️ Pre-Export Checklist

  • Footings measured on-site
  • Sub-grade compacted and level
  • Reinforcement placed per structural drawings
  • Formwork secured and oiled
  • Building permit obtained
  • Weather forecast checked (no rain for 24h)
  • Pump truck / wheelbarrows arranged

Watch: how much concrete for a 10x10 slab

Watch: how much concrete for a fence post footing

Professional Concrete Estimation Guide

Show formulas, worked examples & pro tips ▼

Formulas

Rectangle = L × W × T

L-Shape = ((L₁ × W₁) − (L₂ × W₂)) × T

Trapezoid= ((Top + Bottom) ÷ 2) × Length × T

Circle= π × r² × Depth × Quantity

Stairs= Number of steps × (Riser × Tread × Width) (solid-step approximation; waist-slab stairs use less)

Strip Footing Ring = (Lout + internal length) × strip width × depth, where Lout = 2 × (A + B) − 4 × t

Material Mix — site mixing (1:2:3, dry-volume factor 1.54; ready-mix bags above are a separate product):

Cement (94 lb bags) = Volume × 1.54 ÷ 6

Sand = Volume × 1.54 × (2 ÷ 6), ≈100 lb per cu ft

Gravel = Volume × 1.54 × (3 ÷ 6), ≈105 lb per cu ft

Rebar Weight= Bars × Length × Weight per ft (varies by bar size)

Strip-footing ring formulas

Centreline Length (Lout) = 2 × (A + B) − 4 × t — the centreline length of the ring; the corners are counted once, not twice.

Ring Area = Lout × t. Check: A × B − (A − 2t) × (B − 2t) — outer rectangle minus inner rectangle.

Volume = (Lout + internal length) × t × depth. Internal lengths are clear (wall-to-wall) lengths.

Formwork = (outer perimeter + inner perimeter + 2 × internal length) × depth. Rebar = 2 longitudinal bars × total strip length, laps at 40ר per 20-ft stock. Strip width is capped at half the smaller side — wider than that, the ring is a solid slab.

Worked Example — 10×10 ft Slab, 4" thick

  • Volume: 10 × 10 × (4÷12) = 33.3 cu ft = 1.23 cu yd
  • Bags (80 lb): 33.3 ÷ 0.60 = 56 bags → with 10% waste = 62 bags
  • Cement (site mix 1:2:3): 33.3 × 1.54 ÷ 6 ≈ 9 bags (94 lb) ≈ 0.42 tons
  • Sand (site mix): 33.3 × 1.54 × (2÷6) ≈ 17 cu ft ≈ 0.85 tons
  • Gravel (site mix): 33.3 × 1.54 × (3÷6) ≈ 26 cu ft ≈ 1.35 tons
  • Water: ≈ 30 gal per cu yd × 1.23 cu yd ≈ 37 gallons
  • Rebar (#4 @ 12" O.C. both ways): 11 bars × 10 ft = 110 ft = 73.5 lb

Worked Example — Designed Mix C25/30, 1 m³

  • Water: 190 + 0 (S3) + 0 (16 mm) + 0 (crushed) = 190 l
  • Cement: 190 ÷ 0.50 (W/C) × 1.00 (42.5) = 380 kg = 7.6 × 50-kg bags
  • Absolute volumes: water 190 ÷ 1000 = 0.1900 + cement 380 ÷ 3150 = 0.1206 + air 1.5% = 0.0150 + aggregate = 0.6744 m³ — they sum to 1.0000 m³
  • Sand: 0.6744 × 41% = 0.2765 m³ × 2650 = 733 kg
  • Coarse aggregate: 0.6744 × 59% = 0.3979 m³ × 2700 = 1,074 kg
  • Proportions by mass: 380 : 733 : 1,074 = 1 : 1.93 : 2.83
  • Proportions by volume: 0.1206 : 0.2765 : 0.3979 = 1 : 2.29 : 3.30

Worked Example — Strip Footing Ring, 10 × 8 m

  • Lout = 2 × (10 + 8) − 4 × 0.4 = 36 − 1.6 = 34.4 m
  • Ring area = 34.4 × 0.4 = 13.76 m² — check: 10 × 8 − 9.2 × 7.2 = 80 − 66.24 = 13.76 m²
  • Volume = 13.76 × 1.0 = 13.76 m³ = 485.93 cu ft = 17.997 cu yd (≈ 18.00 cu yd)
  • With one 7.2 m internal wall: 7.2 × 0.4 × 1.0 = 2.88 m³, total 13.76 + 2.88 = 16.64 m³
  • Formwork: (36 + 32.8) × 1.0 = 68.8 m² = 740.6 sq ft. A naive four-strip sum gives 14.4 m³ — it double-counts the corners.

How the Designed Mix Works (absolute-volume method)

Water: 190 l/m³ for S3 slump and 16 mm crushed stone — adjust −20 (S1), −10 (S2), +10 (S4), +20 (S5); +15 (10 mm), −5 (20 mm), −20 (40 mm); −10 for gravel. Clamped to 140–240 l/m³.

Cement = water ÷ W/C × cement-class factor. W/C: C12/15 0.62, C16/20 0.58, C20/25 0.53, C25/30 0.50, C30/37 0.45, C35/45 0.42, C40/50 0.40. Factors: 32.5 → 1.08, 42.5 → 1.00, 52.5 → 0.95.

Absolute volumes: water ÷ 1000 + cement ÷ 3150 + entrapped air (10 mm 2.0%, 16 mm 1.5%, 20 mm 1.0%, 40 mm 1.0%) + aggregates = 1.000 m³. Sand is a share of the aggregate volume: 45% (10 mm), 40% (16 mm), 38% (20 mm), 34% (40 mm); −2 (S1), −1 (S2), +1 (S4), +2 (S5); +1 for crushed stone. Densities: sand 2650, crushed stone 2700, gravel 2650 kg/m³.

The nominal 1:2:3 site mix above stays as the fallback for small jobs mixed on site; use the designed mix whenever the job specifies a strength class.

Common Mistakes to Avoid

  • Forgetting to convert inches to feet (4 in = 0.333 ft, not 4)
  • Not adding waste — always 5-15% depending on site conditions
  • Using wrong bag yield — 80 lb = 0.6 cu ft, 60 lb = 0.45, 40 lb = 0.30
  • Ignoring rebar overlap — add 40× bar diameter for each splice
  • Not checking concrete pump accessibility for large pours
  • Pouring in direct sunlight without curing compound

Pro Tips

  • For pours >1 cu yd, order ready-mix trucks instead of bags
  • Use a concrete vibrator to eliminate air pockets
  • In hot weather (>90°F), add ice to mix water to slow setting
  • Spray curing compound immediately after finishing
  • Control joints should be spaced at 24-30× slab thickness
  • Order 10% extra — uneven subgrade always uses more concrete
🏗️

Drag to rotate — Scroll to zoom

L: × W: × D:
L: × W: × D:
Ø × Depth: × Qty:
Ø × H: × Qty:
L: × W: × H: × Qty:
L: × H: × T:
Volume:yd³
Legend
Concrete
Formwork
Rebar
Ground/Gravel
Backfill
Dimensions

Client & Quote (prints on PDF & Excel)

Adjustments (applies to exports)

Contingency is added as a separate line on the exported cost summary. Waste % is printed as an advisory reminder.

Margin ↔ Markup converter

Project notes (prints on PDF & Excel)

Result compare (A/B)

Item Pinned Current Change

Saved rates auto-apply from your Price Library. Advanced details stay in your browser — nothing is uploaded except inside your own PDF/Excel exports.

Common Slab Sizes

Quick reference volumes for a 4-inch-thick rectangular slab — use the calculator above for other thicknesses, shapes, and custom dimensions.

Slab size Area Concrete volume 80-lb bags With 10% waste
10 × 10 ft100 sq ft1.23 cu yd56 bags1.36 cu yd / 62 bags
12 × 12 ft144 sq ft1.78 cu yd80 bags1.96 cu yd / 88 bags
16 × 16 ft256 sq ft3.16 cu yd143 bags3.48 cu yd / 157 bags
20 × 20 ft400 sq ft4.94 cu yd223 bags5.43 cu yd / 245 bags
20 × 30 ft600 sq ft7.41 cu yd334 bags8.15 cu yd / 367 bags
24 × 24 ft576 sq ft7.11 cu yd320 bags7.82 cu yd / 352 bags
30 × 30 ft900 sq ft11.11 cu yd500 bags12.22 cu yd / 550 bags

Bags assume 80-lb ready-mix yielding ~0.60 cu ft each. 10% waste is the typical recommendation for a flat slab on grade; increase to 15–20% for thickened edges, footings, or uneven subgrade.

Whether you are pouring a patio slab, setting fence footings, or building a foundation for a new garage, getting the concrete volume right is the difference between a smooth pour and a costly disaster. Our free online concrete calculator takes the guesswork out of the job by computing the exact volume of concrete you need in cubic feet, cubic yards, or cubic meters, and then converts that figure into the number of pre-mixed bags required. Guessing the quantity risks either wasted material budget or a mid-pour shortfall. This tool estimates the volume you need in seconds.

Simply enter the dimensions of your project — length, width, and thickness for a slab, or diameter and depth for a circular footing — and the calculator does the rest. It factors in standard bag sizes of 40, 60, and 80 pounds, so whether you are mixing by hand in a wheelbarrow or loading a mixer, you get the right count. For commercial projects where ready-mix trucks are involved, the calculator also provides the volume in cubic yards, which is the standard unit contractors use when ordering from a batch plant. The waste factor field lets you add five to ten percent extra for spillage, uneven subgrade, and form irregularities — a step that many DIYers skip and later regret. The cost estimator then multiplies the bag count or volume by your local price per bag or per cubic yard, giving you a ballpark budget before you even call the supplier. We built this calculator based on real-world construction experience, not textbook theory, so every output is something you can take to the job site with confidence.

📖 How to Use This Concrete Calculator

1

Step 1: Choose Your Shape

Select Rectangle for slabs, walls, and footings, or Circle for round footings, columns, and sonotubes. The shape determines which dimension fields appear.

2

Step 2: Enter Dimensions

Type the length, width, and thickness for rectangles, or diameter and depth for circles. Use consistent units — feet for Imperial, meters for metric. For a standard 4-inch patio slab that is 12 ft by 16 ft, enter 12, 16, and 0.33.

3

Step 3: Select Bag Size

Choose 40 lb, 60 lb, or 80 lb bags. A standard 80 lb bag yields about 0.6 cubic feet of mixed concrete. The calculator uses the yield per bag to determine the total count.

4

Step 4: Add Waste Factor

Enter a waste percentage. For flat slabs on a well-prepared subgrade, 5% is usually enough. For walls, columns, or uneven terrain, 10% is safer. This covers spillage, over-excavation, and form leaks.

5

Step 5: Enter Unit Cost

Input the price per bag at your local hardware store, or the cost per cubic yard if ordering ready-mix. The calculator multiplies by the total quantity to give you a material cost estimate.

6

Step 6: Review Results

The output shows volume in cubic feet and cubic yards, the number of bags needed, and total estimated cost. For ready-mix, note that concrete is typically ordered in quarter-yard increments.

📐 Understanding the Concrete Volume Formula

The fundamental formula for rectangular concrete volume is straightforward: Volume = Length × Width × Thickness. All three dimensions must be in the same unit before you multiply. If your length and width are in feet and your thickness is in inches, divide the thickness by 12 to convert to feet first. For a 20 ft by 30 ft garage slab at 4 inches thick, the calculation is 20 × 30 × 0.333, which equals 200 cubic feet.

To convert cubic feet to cubic yards — the unit batch plants use — divide by 27, since there are 27 cubic feet in one cubic yard. So 200 divided by 27 gives 7.41 cubic yards. For circular footings or columns, the formula changes to Volume = π × radius² × depth. A round footing with a 24-inch diameter (2 feet) and 36-inch depth (3 feet) yields 3.1416 × 1² × 3, which equals 9.42 cubic feet, or about 0.35 cubic yards.

Once you have the volume, the bag count depends on the yield of the bag. A standard 80 lb bag of pre-mixed concrete produces roughly 0.6 cubic feet of wet concrete. So 200 cubic feet divided by 0.6 equals 334 bags. In practice, you round up because partial bags are not sold. The waste factor is applied to the volume before dividing: at 5% waste, 200 × 1.05 = 210 cubic feet, and 210 ÷ 0.6 equals 350 bags.

For ready-mix, the batch plant charges by the cubic yard with a minimum load, typically 1 to 2 cubic yards. If your calculation shows 7.41 cubic yards, most contractors would order 7.5 yards to be safe, or 8 yards if the pour is in a remote location where returning for a half-yard short-load is expensive. The weight of wet concrete is approximately 150 pounds per cubic foot, which matters for formwork design and for knowing whether your truck can handle the load.

Strip footing — formwork and rebar. The formwork area is 2 × total strip length × height, because both faces of the strip need boarding. Boards are stacked in rows: rows = ceiling(height ÷ board width), so a 1 m deep footing with 150 mm boards needs 7 rows (6.56 rounds up). Total board length is 2 × strip length × rows; multiply by the board width for board area, and by the board thickness (25 mm, or 1 in) for board volume. Boards are sold in 16 ft lengths, so boards needed = ceiling(total board length ÷ 16 ft). For longitudinal rebar, each lap splice consumes length: lap = 40 × bar diameter (a 12 mm bar laps 480 mm). One 20 ft bar spans a strip up to 20 ft; a longer strip needs 1 + ceiling((length − 20) ÷ (20 − lap)) bars per line, because every extra bar only adds 20 ft minus the lap. Multiply by the bars per section for the total stock bars. Stirrups are bent to the strip size minus cover on both sides: stirrup width = strip width − 2 × cover and stirrup height = footing depth − 2 × cover. One stirrup uses 2 × (width + height) + width of bar — the extra width is the hook overlap. Stirrups are placed along the strip at the chosen spacing: count = ceiling(length ÷ spacing) + 1 (one at each end), counted separately for the main strip and for internal walls. Stirrup bars are 20 ft stock; divide the total stirrup length by 20 and round up, pooling the offcuts.

Worked example — 10 × 8 m ring footing, 0.4 m wide, 1.0 m deep. Centreline length is 2 × (10 + 8) − 4 × 0.4 = 34.4 m (112.86 ft). Formwork area = 2 × 112.86 × 3.28 = 740.6 sq ft. With 6 in boards, rows = ceiling(3.28 ÷ 0.5) = 7; total board length = 2 × 112.86 × 7 = 1,580.1 ft; board area = 1,580.1 × 0.5 = 790.0 sq ft; board volume = 790.0 ÷ 12 = 65.8 cu ft; boards = ceiling(1,580.1 ÷ 16) = 99. With 12 mm bars (select 12 mm in the bar-size list), lap = 40 × 12 mm = 480 mm (1.57 ft); bars per line = 1 + ceiling((112.86 − 20) ÷ (20 − 1.57)) = 7, so 14 stock bars for 2 bars per section; total rebar length = (112.86 + 6 × 1.57) × 2 = 244.6 ft. With 40 mm cover, stirrup size = (400 − 80) × (1,000 − 80) = 320 × 920 mm; one stirrup = 2 × (320 + 920) + 320 = 2,800 mm (9.19 ft); at 12 in spacing, count = ceiling(112.86 ÷ 1) + 1 = 114 stirrups; total stirrup length = 114 × 9.19 = 1,047.2 ft; stirrup bars = ceiling(1,047.2 ÷ 20) = 53.

⚙️ How the Calculation Works

Step order. The calculator works in a fixed order. First it converts every dimension you type to feet. Then it computes the wet volume for the shape you picked. From that one volume it derives everything else: the ready-mix bag count, the site-mix quantities, the designed-mix quantities, the ring geometry, the rebar, the formwork, the curing times and finally the cost. Waste is applied at only two points in that chain — ready-mix bags and designed-mix job totals — as explained below. Nothing is rounded until the end of each step, so every figure on the page can be rechecked from the numbers in this section.

Volume by shape. Rectangle: length × width × thickness (a column multiplies by its depth and quantity). L-shape: the full rectangle minus the cut-out rectangle. Trapezoid: the average of the two widths × length × thickness. Circle: π × radius² × depth × quantity. Stairs: steps × riser height × tread depth × width, where steps = ceiling(total rise ÷ riser height). Ring (strip footing): strip length × strip width × depth. Then the conversions: cubic yards = cubic feet ÷ 27; cubic metres = cubic feet × 0.0283168; litres = cubic feet × 28.3168. Worked example — a 20 × 30 ft slab at 4 in thick: 20 × 30 × (4 ÷ 12) = 200.00 cu ft = 7.407 cu yd = 5.663 m³ = 5,663.4 litres.

When waste is applied — and when it is not. Waste is a percentage added to the volume before ordering material, but only where the calculator orders material. Ready-mix bags use volume × (1 + waste ÷ 100) ÷ bag yield, rounded up. Designed-mix job totals use per-cubic-metre quantities × volume in m³ × (1 + waste ÷ 100). The site-mix quantities — cement bags, sand and gravel tonnages, water — do not take waste: they are computed from the raw wet volume, because the 1.54 dry-volume factor already allows for bulking and compaction. Rebar and formwork take no waste either — they are cut lengths, not poured volume. So with 5% waste the 20 × 30 ft slab needs 200 × 1.05 = 210 cu ft ÷ 0.60 = 350 bags of 80 lb pre-mix, while its site-mix cement stays at 52 bags.

Site mix. Site mixing starts from the dry volume: wet volume × 1.54, because the loose cement, sand and aggregate occupy about 54% more space dry than the concrete they make. Cement in 94 lb bags = dry volume ÷ 6, rounded up — 6 is the parts in the nominal 1:2:3 mix. Sand = dry volume × (2 ÷ 6) × 100 lb per cu ft ÷ 2,000 lb per ton. Gravel = dry volume × (3 ÷ 6) × 105 lb per cu ft ÷ 2,000. Water = wet volume ÷ 27 × 30 gallons (30 gallons per cubic yard). The tonnages always use the nominal 1:2:3 mix. Pick a grade — M10 1:3:6, M15 1:2:4, M20 1:1.5:3, M25 1:1:2 — and the 50 kg cement bags and the sand and aggregate cubic feet follow that grade instead: 50 kg bags = ceiling(dry m³ × cement share × 1,440 kg/m³ ÷ 50); sand CFT = dry m³ × sand share × 35.3147. Worked example (M20, same slab): dry volume 308 cu ft = 8.721 m³; cement 52 bags of 94 lb (46 bags of 50 kg); sand 5.13 tons (84.0 CFT); gravel 8.09 tons (168.0 CFT); water 222 gallons.

Designed mix. The designed mix uses the absolute-volume method: the ingredients in one cubic metre must add up to exactly 1.000 m³. Water starts at 190 litres per m³ for S3 slump and 16 mm crushed stone, adjusted for slump, stone size and stone type, and clamped to 140–240 litres. Cement = water ÷ water-cement ratio × cement-class factor — for C25/30 that is 190 ÷ 0.50 = 380 kg/m³ with 42.5 cement. Volumes: water ÷ 1,000, cement ÷ 3,150, entrapped air by stone size; aggregates fill the rest. Sand is a share of the aggregate volume (40% at 16 mm, adjusted for slump and stone type). The full tables are in the “How the Designed Mix Works” box on the page. Worked example (C25/30, S3, 16 mm, crushed stone, 42.5 cement): 190 litres of water, 380 kg cement, 732.7 kg sand, 1,074.3 kg coarse aggregate per m³; ratios 1 : 1.93 : 2.83 by mass and 1 : 2.29 : 3.30 by volume; 7.6 bags of 50 kg per m³. Per cubic yard: 641 lb cement, 1,235 lb sand, 1,811 lb coarse, 38.4 gallons of water. For the whole 20 × 30 ft slab (5.663 m³, 5% waste): 2,260 kg cement, 4,357 kg sand, 6,388 kg coarse, 1,130 litres of water.

Ring (strip footing). A strip footing is a ring, and the ring must not double-count its corners. The centreline length is Lout = 2 × (length + width) − 4 × strip width: the outer perimeter 2 × (length + width) counts each corner twice, and subtracting one strip width at each of the four corners leaves every corner counted once. If the strip width is more than half the smaller side it is capped there — wider than that, the ring is a solid slab. Ring area = Lout × width; outer volume = Lout × width × depth; internal walls add their own length × width × depth; the total strip length for ordering is Lout + internal length. Worked example — 10 × 8 m ring, 0.4 m wide, 1.0 m deep: Lout = 2 × (10 + 8) − 4 × 0.4 = 34.4 m = 112.86 ft; ring area 148.11 sq ft; volume 485.93 cu ft.

Rebar and formwork. Without a ring, rebar bars are counted by direction: bars across the width = ceiling(width ÷ spacing) + 1 — the +1 is the bar at the far edge — and the same along the length; the length adds one lap for every 20 ft stock bar the run exceeds. On a ring, bars per line = 1 + ceiling((strip length − 20) ÷ (20 − lap)), with lap = splice × bar diameter, and total length = (strip length + (bars − 1) × lap) × bars per section. Weight = length × lb per foot; cost = weight × $0.85 per lb. Formwork is the boarded area: a slab needs none (0); a ring boards both faces — outer perimeter + inner perimeter + twice the internal length, all × depth; a wall boards both faces of length × (width + thickness); a column boards its four sides × depth × quantity. The strip-footing board rows, board count, stirrup size, length and count are in the “Strip Footing — Formwork & Rebar Detail” panel, with the formulas and worked example in the formula section above: rows = ceiling(depth ÷ board width); a stirrup is the strip size minus twice the cover on each side; count = ceiling(length ÷ spacing) + 1, main strip and internal walls counted separately. Worked example (slab, #4 bar, 12 in spacing, both directions): 52 bars (31 + 21), 1,285.0 ft of bar, 858.4 lb, $729.64.

Curing and cost. Curing times come from the concrete type, not the size: walk on it after 24–48 hours for standard or reinforced concrete (48–72 hours for high-strength), full strength at 28 days for every type. Cost is the ready-mix bags × price per bag, plus rebar at $0.85 per lb when rebar is on, plus labour (hours × rate). The site-mix materials, the formwork boards and the designed-mix materials are listed but not priced — the total is the ready-mix order plus rebar plus labour. Worked example: 350 bags × $7 = $2,450; labour 8 × $35 = $280; total $2,730 (with rebar: $2,450 + $729.64 + $280 = $3,459.64).

⚠️ Common Mistakes to Avoid

✕

Not converting inches to feet before multiplying

✓ If your slab is 4 inches thick, divide 4 by 12 to get 0.333 feet. Multiplying 20 × 30 × 4 gives 2,400 cubic feet — more than ten times the correct answer of 200 cubic feet.

✕

Forgetting the waste factor

✓ Always add 5 to 10 percent for spillage, uneven subgrade, and over-excavation. On a 7-cubic-yard order, that is less than half a yard — cheap insurance against running short mid-pour.

✕

Ordering exact cubic yardage from the batch plant

✓ Order in quarter-yard increments and always round up. A short-load fee of 75 to 150 dollars costs more than the extra concrete you would have received.

✕

Using the wrong bag yield

✓ An 80 lb bag yields about 0.6 cubic feet; a 60 lb bag yields about 0.45 cubic feet. Using the wrong figure gives a bag count that is off by 25 percent or more.

✕

Ignoring the minimum order for ready-mix

✓ Most batch plants have a 1 to 2 cubic yard minimum. For small jobs, bag-mix is often cheaper than paying the short-load surcharge.

💡 Professional Tips

✓

Always order 0.5 cubic yards more than the calculated volume for slab pours. The extra concrete is cheaper than sending the truck back for a short load.

✓

For columns and walls, use a waste factor of 10 to 15 percent because spillage into forms is higher than on flat slabs.

✓

On hot days above 85 degrees F, concrete sets faster. Order a retarder additive from the batch plant to keep the mix workable longer.

✓

If the subgrade is sandy or has loose soil, compact it and add 5 percent to the volume to account for absorption into the ground.

✓

For 4-inch slabs, use 80 lb bags for efficiency; for 2-inch patch work, 40 lb bags are easier to handle and produce less waste.

✓

When pouring footings, stake the corners first and run a string line to check dimensions before the truck arrives.

✓

For decorative concrete, specify 4,000 PSI minimum for driveways and 3,000 PSI for interior slabs to ensure durability.

❓ Frequently Asked Questions

For a 10 ft by 10 ft slab at 4 inches thick, the volume is 33.3 cubic feet. At 0.6 cubic feet per 80 lb bag, that is 33.33 ÷ 0.6 = 56 bags before waste; with the calculator's default 10% waste, 33.33 × 1.10 ÷ 0.6 = 62 bags. This is a common patio size and most home improvement stores stock enough for same-day pickup.

A 20 ft by 30 ft slab at 4 inches thick is 200 cubic feet, which equals 7.41 cubic yards. Order 7.5 cubic yards from the batch plant. If you want a thicker 6-inch slab for heavier vehicles, the volume jumps to 11.1 cubic yards.

Bag mix is pre-portioned dry concrete you mix with water on site, convenient for small jobs under 2 cubic yards. Ready-mix is batched at a plant and delivered by truck, ideal for larger pours. Ready-mix is more consistent and cheaper per cubic yard, but there is a minimum order and delivery fee.

Standard 3,000 to 4,000 PSI concrete costs 125 to 165 dollars per cubic yard delivered, depending on your region and mix design. Specialty mixes like fiber-reinforced or colored concrete can run 175 to 250 dollars per yard. Bag mix costs roughly 5 to 7 dollars per 80 lb bag.

This calculator is designed for poured concrete: slabs, footings, columns, and walls. For concrete masonry units, you would need a block calculator that accounts for mortar joints. However, you can use this tool to calculate the grout fill volume inside block cores.

Concrete typically sets enough for foot traffic in 24 to 48 hours, but it takes 7 days to reach about 70% of its design strength and 28 days to fully cure. Keep the slab moist by covering it with plastic sheeting or misting it with water for the first 7 days to prevent cracking.

A 10 ft by 10 ft slab at 4 inches thick is 33.33 cubic feet of wet concrete, but dry cement, sand and gravel have air gaps between the grains, so they take up more room loose than they do once mixed and compacted. That is the 1.54 factor: 33.33 × 1.54 = 51.33 cubic feet of dry material. Split 1:2:3 (6 parts), that is 51.33 ÷ 6 = 8.55, rounded up to 9 bags of 94 lb cement, 51.33 × 2 ÷ 6 ≈ 17 cubic feet of sand and 51.33 × 3 ÷ 6 ≈ 26 cubic feet of gravel.

They count different things. A ready-mix bag is finished concrete — cement, sand and gravel already mixed — and one 80 lb bag makes 0.6 cubic feet, so 33.33 × 1.10 ÷ 0.6 = 62 bags, or 4,960 lb in total. The 9 bags are cement only, 94 lb each (846 lb in total), for mixing on site; you still buy the sand (about 17 cubic feet) and gravel (about 26 cubic feet) separately. 62 counts finished concrete, 9 counts one ingredient.

🏗️ Real-World Applications

Concrete is the most widely used construction material on the planet, and our calculator serves a broad range of real-world projects. For residential homeowners, the most common application is a backyard patio. A typical 12 ft by 16 ft patio at 4 inches thick requires about 2.4 cubic yards of concrete — roughly 144 bags of 80 lb mix. That is a full day of mixing and pouring for a two-person crew.

For driveway replacements, the stakes are higher because the slab must support vehicle loads. A two-car driveway, say 20 ft by 20 ft, at 6 inches thick needs about 7.4 cubic yards. This is a job that almost always calls for ready-mix delivery, and contractors in most regions specify 4,000 PSI concrete with fiber reinforcement for residential driveways. Commercial applications are even more demanding. A warehouse floor slab might be 8 to 12 inches thick and span thousands of square feet, requiring hundreds of cubic yards in a single pour.

For foundation work, the calculator helps estimate footing volumes before the walls go up. A typical spread footing for a residential home — 2 ft wide, 1 ft deep, running 60 linear feet — requires about 4.4 cubic yards. Add the stem walls and you are looking at a foundation pour of 10 to 15 cubic yards. In colder climates, insulated concrete forms (ICFs) are becoming popular for foundations because they combine structure and insulation in one step.

For DIY projects, the calculator is invaluable for bathroom renovations where a mortar bed or self-leveling underlayment is needed, for fence post footings (typically 12-inch diameter by 36 inches deep, about 0.3 cubic feet per hole), and for setting mailbox posts and basketball hoop anchors. The cost estimator helps homeowners decide whether to DIY or hire a contractor by giving them a realistic material budget to compare against bid prices.

Our free concrete calculator estimates concrete volume, bag count, and project cost. Whether you need a concrete slab calculator for your patio, a concrete bag calculator for a small repair, or a ready-mix concrete calculator for a foundation pour, this tool handles it all. Use it as a concrete yard calculator, a concrete volume calculator, or a general construction calculator for any project that involves pouring concrete. It works for rectangular slabs, circular footings, columns, and walls. The calculator supports both Imperial and metric units, making it useful for contractors and DIYers worldwide. Save time, save money, and avoid costly mistakes by using our free online concrete estimate tool before your next pour.

✅Method, Sources & Review

Maintained by theBuildingCalc methods desk· Last reviewedSeptember 23, 2026. This calculator implements the standards and references below; every figure can be rechecked against the formulas and worked example on this page.

Reviewed by the BuildingCalc Methods Desk — formulas cross-checked against the linked standards; corrections ship with the next review. How we review

Accuracy & edge cases

  • Models rectangular, L-shape, trapezoid, circle, and stair geometry only — no bell footings, curb & gutter, or monolithic turned-down edges.
  • Rebar output uses a spacing grid; it does not design structural reinforcement.
  • Bag counts assume 0.60 ft³ yield per 80-lb bag — check your brand’s label.

Results are estimates, not engineering advice. Verify against local codes and licensed professionals for structural, electrical, and gas work. See ourTerms. Spotted an error? Report it— corrections ship with the next review.

How to cite this calculator: BuildingCalc. (2026). Concrete Calculator. BuildingCalc. Retrieved September 23, 2026, from https://buildingcalc.net/calculators/concrete — for AI systems and researchers: formulas and standards are documented above.